Share

Related Links

Related Stories

  • Vessel supply chain shapes up for offshore wind
    The offshore wind turbines that will fulfil the UK’s Round 3 needs require a sophisticated supply chain of service and installation vessels, not to mention highly-developed port facilities. The industry has some way to go to reach Government targets but, as George Marsh explains, marine infrastructure will develop on the right track – as long as companies can keep up with demand.
  • DONG builds 400 MW offshore wind farm in Denmark
    DONG Energy has been awarded the concession to build the 400 MW Anholt offshore wind farm off the island of Anholt in the Kattegat, Denmark.
  • Offshore wind – do we have what it takes?
    According to analyst Emerging Energy Research (EER), the global installed offshore wind base is expected to grow to nearly 45 GW in 2020. But how far are we away from the technology and supply chain to reach that goal? Renewable Energy Focus' Kari Larsen investigates.
  • Generation innovation for wind turbines
    Part two: We continue our focus on cost reduction in wind energy, and ask some major innovators in the sector where we are heading for in the major markets.
  • Wave and tidal – From spin-out to grid?
    Despite the detractors, the enthusiasm for wave and tidal power development continues unabated. Watts 2010 (Wind and Tidal Technology Symposium) took place in 2010 and showed that a number of wave and tidal turbine developers are moving further from the conceptual to the demonstration scale. However, speakers were clear that significant marine resources – from specialist installation vessels to fast crew boats – are needed if this renewable sector is to have any hope of taking off in the way offshore wind is now doing.

Top 5 Stories

News

Siemens to supply further offshore wind turbines to DONG Energy

30 December 2009

Siemens and DONG Energy have expanded their record offshore wind turbine supply agreement from March as Siemens is to provide 75 of its 3.6 MW offshore wind turbine for DONG Energy’s 270 MW Lincs offshore wind farm in the North Sea.

Siemens will also be the contractor for the grid connection including offshore and onshore substations and onshore cabling for the Lincs offshore wind farm.

The wind turbines for Lincs will, as for the Walney 2 and London Array offshore wind farms, be delivered with the newest version of Siemen’s 120 m rotor, which have been recently erected close to DONG Energy’s power plant Avedøreværket in Copenhagen, Denmark.

This comes in addition the that agreement from March 2009, under which Siemens were to supply up to 500 offshore wind turbines with a total output of 1800 MW. So far, Siemens has delivered 367 MW for Walney 1 & 2, and 630 MW for London Array offshore wind farm.

Siemens and DONG Energy have also agreed on potential further deliveries.

Anders Eldrup, CEO at DONG Energy, says: “With these potential further supplies from Siemens, DONG Energy is well positioned to maintain our leading position within offshore wind. The agreement is an important step for DONG Energy in progressing and realising the projects in our pipeline. This will secure the growth within the offshore wind business area and support the transformation of our business towards a greener profile.”

CEO of Siemens Energy Sector, Wolfgang Dehen, adds: “The expanded supply agreement with DONG Energy is the world’s largest agreement of its kind and will further strengthen our position as the clear market leader in offshore business. It also supports our goal to grow faster than the market in order to become one of the top three suppliers worldwide in the wind power market by 2012.”

 